808264746
Southeast Supply Header, LLC
Critical notice
03/09/2020
03:30:00 PM
06/07/2020
03:30:00 PM
94275
Initiate
Capacity Constraint
03/09/2020
03:30:00 PM


No response required


SESH Spring Planned Outages


Notice Text:

Southeast Supply Header, LLC - Critical Notice

Subject: SESH Planned Outages

Pursuant to Section 15 of the General Terms and Conditions of Southeast Supply Header, LLC's ("SESH") FERC Gas Tariff ("Tariff"), SESH notifies its shippers of the scheduled outages described below.During these outage periods, the quantity of available capacity on the SESH system will be limited as set forth below.

Delhi Compressor Station Outage:March 20 - 21, 2020:
On Gas Day March 20, 2020, SESH's capacity will be limited to approximately (i) 421,000 Dth /d through the Delhi Compressor Station, (ii) 602,000 Dth /d through the Gwinville Compressor Station and (iii) 600,000 Dth/d through the Lucedale Compressor Station.

Additionally, on Gas Day March 21, 2020, SESH's capacity will be limited to approximately (i) 841,000 Dth /d through the Delhi Compressor Station, (ii) 1,022,000 Dth /d through the Gwinville Compressor Station and (iii) 1,020,000 Dth/d through the Lucedale Compressor Station.

Gwinville Compressor Station Outage: March 27 - 28, 2020:
Beginning on Gas Day March 27, 2020 and continuing through Gas Day March 28, 2020, SESH's capacity will be limited to approximately (i) 794,000 Dth /d through the Delhi Compressor Station, (ii) 977,000 Dth /d through the Gwinville Compressor Station and (iii) 974,000 Dth/d through the Lucedale Compressor Station.

Lucedale Compressor Station Outage:March 29:
On Gas Day March 29, 2020, SESH's capacity will be limited to approximately (i) 686,000 Dth /d through the Delhi Compressor Station, (ii) 868,000 Dth /d through the Gwinville Compressor Station and (iii) 868,000 Dth/d through the Lucedale Compressor Station.

During these outage periods all receipt and delivery points will be operational.

If nomination flow patterns change significantly during this outage, SESH will post revised capacities to reflect these changes.

If any of the information above changes, SESH will promptly update this posting.

If you have any questions regarding this posting, please contact your Account Representative.